Concrete Estimate Template: Copy It, With a Priced 20x20 Pad
For every trade: Contractor Estimate Template With Good, Better, and Best Options
A concrete estimate template has 11 parts and three prices
A concrete estimate template lists the slab size and thickness, the cubic yards, the scope of work, three options with one price each, add-ons, what is not included, payment terms, and the date the price is good through. In our worked example below, a 20 by 20 foot driveway pad comes to $4,050, $4,640, or $5,140 for good, better, and best, using ready-mix at $148 to $156 a yard from Gehring Construction's price list and the prices one Menards store listed on November 9, 2026.
Estimate, quote, or bid: on this page they mean the same thing, a written price the customer can say yes to.
The 11 parts:
- Your business name, phone, and license number, if your state or city issues one
- The customer's name and the job address
- Size in feet, thickness in inches, and square feet
- Cubic yards of concrete and the mix
- The scope every option includes: dig out, base, forms, finish, joints, and cleanup
- Three options, good, better, and best, each with one price
- Add-ons the customer can tick, each with its own price
- What is not included
- Payment terms
- Start week and how many days the job takes
- The date the price is good through
Give the customer one price per option, and keep the cost sheet for yourself. The sections below build that cost sheet line by line. For plumbing, electrical, and other trades, use our contractor estimate template.
Copy this concrete estimate template
Fill in the brackets and delete any line that does not apply.
Concrete estimate for [customer name], [job address]
[Business name], [phone]. License [number, if your state or city issues one]. Insured with [insurer].
Estimate date: [date]. This price is good through [date, 30 days out or less]. After that, we re-price concrete and materials.
Job: [driveway, patio, sidewalk, or pad], [length] by [width] feet, [square feet] square feet.
Every option includes: dig out for the base and slab, [inches] inches of compacted gravel base, wood forms, ready-mix concrete, [broom] finish, control joints about every [feet] feet, form removal, and cleanup.
Option 1, Good: [thickness]-inch slab, [mix], [fiber, mesh, or none]. $[price]
Option 2, Better: [thickness]-inch slab, [mix], [rebar size and spacing], cure and seal. $[price]
Option 3, Best: [thickness]-inch slab, [mix], [rebar size and spacing], cure and seal. $[price]
Add-ons, pick any: Cold-weather pour, $[price]. Cure and seal with Option 1, $[price]. Pump truck, if the mixer can't reach the forms, $[price].
If we find soft soil, roots, or old concrete under the sod: $[price] a ton for extra base, or $[price] an hour.
Not included: [hauling away the dirt, removing old concrete, permits, or anything else you won't touch].
Permit: [included, or the customer pulls it], [city].
Sales tax: [included, or $amount].
Payment: [deposit, if any] to schedule. Balance due [when].
Start: week of [date], weather permitting. The job takes about [number] days.
Questions: call or text [your name] at [phone].
Keep the line about what you find when you dig. You can't see under the sod until the crew opens it, and a per-ton or per-hour price the customer agrees to now saves an argument on the job.
Figure cubic yards from square feet and thickness, then add 4 to 10 percent
Ready-mix is sold by the cubic yard, which is 27 cubic feet. Multiply length by width in feet, multiply by the thickness in inches divided by 12, then divide by 27.
| Thickness | Cubic yards per 100 square feet |
|---|---|
| 4 inches | 1.23 |
| 5 inches | 1.54 |
| 6 inches | 1.85 |
The figures are arithmetic. For example, a 20 by 20 foot pad 4 inches thick is 400 x 4 ÷ 12 ÷ 27 = 4.94 cubic yards.
Then order extra. The National Ready Mixed Concrete Association tells buyers to order more than their figured volume "by at least 4 to 10 percent," for waste, extra thickness, forms that bow, and other surprises. The same page shows how fast a small miss adds up: 1/8 inch extra on a 4-inch slab is a 3% shortage. It also says to recheck the volume near the end of the pour, tell the plant in time to adjust the last loads, and avoid a short load to finish.
Watch small loads. Gehring Construction charges $50 a load under 4 yards. As an example, a 10 by 10 foot sidewalk pad at 4 inches is 1.23 yards, plus 10% is 1.36, so you'd order 1.5 yards, and the $50 adds $33.33 a yard. Put it on that estimate as its own line, or the small job eats it.
In our worked example we add 10% and round up to the next half yard. The 4-inch pad is 4.94 x 1.10 = 5.43, so we order 5.5 yards. The same pad at 5 inches is 6.17 yards, plus 10% is 6.79, so 7 yards.
Ready-mix prices from two plants, opened November 9, 2026
Gehring Construction in Columbus, Nebraska, posts its ready-mix prices: 12 mixes from $140 to $164 a yard. The list took effect January 1, 2026, and says sales tax is not included and prices are "subject to change without notice." These are the four mixes our example uses.
| Gehring mix | Cement | Price a yard |
|---|---|---|
| SG-3000, sand gravel | 6 bag | $148.00 |
| SG-3500, sand gravel | 6.5 bag | $152.00 |
| SG-4000, sand gravel | 7 bag | $156.00 |
| L-4000, 30% rock | 6.5 bag | $164.00 |
The extras on the same list are where small jobs and winter jobs change price:
| Gehring extra | Price |
|---|---|
| Fiber mesh | $8.00 a yard |
| Hot water | $5.00 a yard |
| Winter service, December 1 to March 15 | $5.00 a yard |
| Calcium chloride, per 1% | $5.50 a yard |
| Small load, under 4 yards | $50.00 a load |
| Mileage, one way over 20 miles | $3.00 a mile, per load |
| Truck held over 1 hour | $120.00 an hour |
The yard price is only part of what you pay. Supreme Concrete in Los Angeles lists 3000 PSI 1-inch rock at $127.05 a yard and 4000 PSI at $132.00, less than Gehring. Its sample quote, a 10-yard order to Burbank, then adds $363.88 for one delivery trip to Zone A, its close-in Valley zone, and a $55 environmental fee per trip. As an example, if 5.5 yards of its 4000 PSI went out on one trip with those charges, that is $726.00 plus $418.88, or $208.16 a yard before its 9.5% sales tax. Gehring lists no mileage charge inside 20 miles, so its SG-4000 stays at $156 a yard on the same order.
Supreme also lists pumping at $300 to set up plus $13 a yard. That belongs on the estimate as an add-on whenever the mixer can't back up to the forms.
Ask your plant for its list and work out the delivered yard: the mix, the trip, the fees, and the tax, divided by the yards you order.
Rebar, forms, base, and sealer prices on November 9, 2026
These are the prices one Menards store, in Westover, West Virginia, showed on menards.com on November 9, 2026, before the 11% rebate Menards listed and before sales tax. The gravel is from Plaisted Companies in Minnesota. Swap in your own suppliers.
| Material | Size | Price |
|---|---|---|
| Grade 60 rebar, #4 | 1/2 inch x 20 feet | $8.99 a bar |
| Plastic rebar chair | One | $0.33 |
| Rebar tie wire, 16 gauge | 340-foot roll | $9.69 |
| Reinforcing mesh panel | 4 x 8 feet | $7.79 |
| Construction lumber | 2 x 6 x 16 feet | $13.92 |
| Concrete forming stake | 18 inches | $3.99 |
| Tremco Vulkem Pro Series Concrete Cure & Seal | 1 gallon | $26.99 |
| Plaisted Class 5 gravel | 1 ton | $19.95, plus $150 an order to haul to its Zone 1 |
How much of each:
- Rebar. Bars each way = (side length minus the edge cover) ÷ spacing, rounded up, plus 1. Our example keeps bars 3 inches in from each edge. On a 20-foot side at 24 inches, 19.5 ÷ 2 rounds up to 10 spaces, so 11 bars each way and 22 in all. At 18 inches it is 13 spaces, 14 bars each way, and 28 in all.
- Base. Plaisted's FAQ says a ton of rock covers 70 square feet 3 inches deep. At 4 inches that is about 52.5 square feet a ton, so 400 square feet takes 7.6 tons. We order 8.
- Forms. The perimeter ÷ 16 feet gives the boards. A 20 by 20 pad is 80 feet, so 5 boards; we price 6 for cuts. Leave the line off if you reuse forms.
- Sealer. Tremco's Vulkem Cure & Seal page lists 300 to 400 square feet a gallon for each coat, so one coat on 400 square feet takes 1 to 1.3 gallons. We price 2 gallons.
- Joints. The NRMCA's joint guide puts joints no farther apart than 24 to 36 times the slab thickness, about 10 feet for a 4-inch slab and never more than 15 feet, with panels square or close to it and the groove at least a quarter of the slab deep, and at least 1 inch. One joint each way turns a 20 by 20 pad into four 10 by 10 foot panels.
Price labor by the crew hour, then add payroll taxes and insurance
Labor is the biggest line in our worked example: 43% of the good option's cost. Price it from the hours your crew will spend on each step, times what each hour costs you.
What an hour costs:
- Pay. The median cement mason and concrete finisher earned $27.41 an hour, or $57,020 a year, in May 2025, according to the Bureau of Labor Statistics. Use what you actually pay.
- Payroll taxes. Employers pay 6.2% for Social Security and 1.45% for Medicare, so 7.65% on top of wages, per the IRS.
- Insurance. Insureon's concrete contractor page, updated July 27, 2026, lists averages of $119 a month for general liability and $240 a month for workers' compensation for small concrete businesses that buy through Insureon. Spread that across the jobs you do in a month.
- Equipment and truck. Skid steer, plate compactor, mixer trailer, fuel, and the truck payment. Give each job its share.
List the hours by step: dig out and grade, spread and compact the base, set forms, tie rebar, pour and finish, cut joints, strip forms, and seal. Our example assumes a crew of three for 8 hours on day one and 6 hours on pour day, then one person for 2 hours to strip forms later, so 44 hours for the good option. Tying rebar adds 3 hours and sealing adds 1 for the better option. The tighter grid adds 2 more for the best.
Then add profit by dividing your total cost by 1 minus the margin you want. For a 25% margin, divide by 0.75: a $3,000 cost becomes a $4,000 price. Adding 25% to the cost gives $3,750, which is a 20% margin. Our guide to raising your prices explains margin and markup.
Last, divide each option's price by its square feet. If the number is far from your last few jobs, find the line that moved before you send it.
Sam is the AI office manager that never sleeps.
He books jobs, sends invoices, and answers your customers, all by text. He checks with you before anything goes out.
Free plan, no credit card. Sam answers new customers on Pro. Or text (833) 365-7267.
Hi, I'm Sam. Text me what you need done and I'll take care of it.
How do I get started?
Worked example: one 20 by 20 foot pad at three prices
This example is arithmetic, not a quote. It uses Gehring's ready-mix prices, the Menards and Plaisted prices in the table above, and these assumptions of ours: new pad on bare ground, 4 inches of Class 5 base, no mileage charge, the dirt spread on the property, 24 stakes, $300 for equipment, truck, and fuel, four jobs a month, $27.41 an hour for everyone, and a 25% margin.
Costs every option shares
| Line | Math | Cost |
|---|---|---|
| Form boards, 2 x 6 x 16 | 6 x $13.92 | $83.52 |
| Stakes | 24 x $3.99 | $95.76 |
| Gravel base | 8 tons x $19.95, plus $150 haul | $309.60 |
| Insurance share | ($119 + $240) ÷ 4 jobs | $89.75 |
| Equipment, truck, and fuel | Assumed | $300.00 |
| Shared costs | $878.63 |
The three options. Concrete is SG-3000 at $148 or SG-4000 at $156, plus $8 a yard for fiber.
| Good | Better | Best | |
|---|---|---|---|
| Slab | 4 inches, 6-bag mix, fiber | 4 inches, 7-bag mix, fiber, #4 rebar every 24 inches, sealed | 5 inches, 7-bag mix, fiber, #4 rebar every 18 inches, sealed |
| Concrete | 5.5 yards x $156 = $858.00 | 5.5 yards x $164 = $902.00 | 7 yards x $164 = $1,148.00 |
| Rebar, chairs, and tie wire | $0 | 22 bars, 60 chairs, 1 roll = $227.27 | 28 bars, 100 chairs, 1 roll = $294.41 |
| Sealer, 2 gallons | $0 | $53.98 | $53.98 |
| Labor hours | 44 | 48 | 50 |
| Labor plus 7.65% payroll tax | $1,298.30 | $1,416.33 | $1,475.34 |
| Shared costs | $878.63 | $878.63 | $878.63 |
| Total cost | $3,034.93 | $3,478.21 | $3,850.36 |
| Price at a 25% margin (cost ÷ 0.75) | $4,050 | $4,640 | $5,140 |
| Per square foot | $10.13 | $11.60 | $12.85 |
Prices are rounded up to the next $10.
Add-ons, at the same 25% margin. A cold-weather pour adds Gehring's $5 winter service and $5 hot water, $10 a yard: $55 on 5.5 yards, priced at $80, or $70 on 7 yards, priced at $100. Cure and seal on the good option is $53.98 of sealer plus 1 hour of labor with payroll tax ($29.51), priced at $120.
Here is the template filled in for a customer named Sarah M.:
Concrete estimate for Sarah M., [job address]
Job: driveway parking pad, 20 by 20 feet, 400 square feet.
Every option includes: dig out for the base and slab, 4 inches of compacted gravel base, wood forms, ready-mix concrete, broom finish, control joints that make four 10 by 10 foot panels, form removal, and cleanup.
Option 1, Good: 4-inch slab, 6-bag mix with fiber. $4,050
Option 2, Better: 4-inch slab, 7-bag mix with fiber, #4 rebar every 24 inches each way, cure and seal. $4,640
Option 3, Best: 5-inch slab, 7-bag mix with fiber, #4 rebar every 18 inches each way, cure and seal. $5,140
Add-ons, pick any: Cold-weather pour, December 1 to March 15, $80 ($100 with Option 3). Cure and seal with Option 1, $120.
Not included: hauling away the dirt we dig out, removing old concrete, and permits.
This price is good through December 9, 2026.
Write a good-through date of 30 days or less
Housecall Pro's estimate guide says an expiration date is "typically 30, 60, or 90 days," and its sample line reads "Price valid for 30 days." For concrete, keep it at 30 days or less, for three reasons.
- Ready-mix keeps rising. The government's producer price index for ready-mix concrete went from 393.592 in September 2025 to 402.820 in September 2026, up 2.3% in a year.
- Plants re-price on a date. Gehring's list took effect January 1, 2026. If your plant also changes prices in January, an estimate you write in December should say the price holds only for pours before then.
- Winter costs more. Gehring adds winter service from December 1 to March 15. A pad priced in November and poured in December costs more, which is why the template lists the cold-weather pour as its own add-on, with the dates.
Say what happens after the date, in one plain line: "After that, we re-price concrete and materials." Then the customer knows the price isn't a trick when it changes.
If you sell the job in the customer's home, read the FTC's Cooling-Off Rule page. The rule covers sales of $25 or more made at the buyer's home, and the buyer can cancel for a full refund until midnight of the third business day after the sale. It lists exceptions, including repairs or maintenance the customer asked you to come do. A new pad is neither, so the rule can apply.
Follow up on day 3, day 7, and the week the price runs out
A quiet estimate isn't always a no. The customer may be comparing, waiting on a spouse, or unsure which option to pick. A short text at the right time gets the answer either way. Copy these and change the names.
Day 3:
Hi Sarah, it's Dave with [Your Town] Concrete. Did the estimate for the driveway pad come through? Happy to walk you through the three options.
Day 7:
Hi Sarah, Dave again. I have pour days open the weeks of [date] and [date]. If one of the options works for you, I can hold a day.
The week the price runs out:
Hi Sarah, the price on your driveway pad is good through [date]. After that I need to re-price the concrete. Want me to hold it?
After it runs out:
Hi Sarah, concrete prices changed since your estimate, so here is an updated one, still with three options. The new price is good through [date].
Three options help here too. A customer who thinks the 5-inch slab with the tight grid is more than they need has a 4-inch pad to say yes to instead of saying nothing. When you send the invoice after the pour, our contractor invoice template has the wording.
Where ServicePro fits
ServicePro is home services software. Every business can write an estimate with options and add-ons, like the three slabs and the cold-weather pour above. The customer opens it on their phone with no login, picks an option, ticks any add-ons, and approves, and the approved lines become the job's lines, ready to invoice. An estimate with no answer after 3 days shows on your Today screen so you can call or text the customer. Free is $0 with no card and builds a website with a booking page from your Google Business Profile. Pro is $99 a month with no contract and adds a toll-free number that forwards to your cell, plus two-way texting once carrier verification clears, which can take several business days.
ServicePro does not figure yards or price concrete, so build each price on your own cost sheet first. Estimates have no good-through date, e-signature, photos, or PDF or printed copy, so tell the customer the good-through date when you send it. Get the free website.
How this post was made: drafted with AI from the sources linked on this page. Figures and links were checked on November 9, 2026.
Frequently Asked Questions
What should a concrete estimate include?
A concrete estimate should have 11 parts: your business details, the customer and job address, size and thickness, cubic yards and the mix, the scope every option includes, three options with one price each, add-ons, what is not included, payment terms, start week and length, and the date the price is good through. Keep the cost sheet with yard, rebar, base, and labor costs for yourself, and give the customer one price per option.
How do you figure cubic yards for a concrete estimate?
Multiply length by width in feet, multiply by the thickness in inches divided by 12, and divide by 27. A 4-inch slab takes 1.23 cubic yards per 100 square feet, so a 20 by 20 foot pad is 4.94 yards. The National Ready Mixed Concrete Association says to order at least 4 to 10 percent more than that for waste and surprises. Our example adds 10% and orders 5.5 yards.
How much does ready-mix concrete cost per yard in 2026?
It depends on the plant and the delivery. Gehring Construction in Columbus, Nebraska, lists $140 to $164 a yard on prices effective January 1, 2026, before tax, with a $50 charge on loads under 4 yards. Supreme Concrete in Los Angeles lists 4000 PSI at $132 a yard but adds $363.88 a trip in its sample quote plus a $55 fee, so price the delivered yard, not just the mix.
How do you price labor on a concrete job?
Multiply the crew hours for each step by what an hour costs you. The Bureau of Labor Statistics puts the median cement mason and concrete finisher at $27.41 an hour in May 2025. Add 7.65% for employer payroll taxes, a share of insurance, such as Insureon's $119 a month for general liability and $240 for workers' compensation, and your equipment. Then divide the total cost by 0.75 for a 25% margin.
How long should a concrete estimate be good for?
Use 30 days or less. Housecall Pro says expiration dates are typically 30, 60, or 90 days, but concrete moves: the producer price index for ready-mix rose 2.3% from September 2025 to September 2026. Plants re-price on a date, and some add winter charges, like Gehring's $5 a yard from December 1 to March 15. Write the date on the estimate and say you re-price after it.
What does a 20 by 20 concrete pad cost?
In our worked example, which is arithmetic and not a quote, a 20 by 20 foot pad on 4 inches of gravel base prices at $4,050 for a 4-inch slab with fiber, $4,640 with rebar and sealer, and $5,140 for a 5-inch slab with a tighter rebar grid. That is $10.13 to $12.85 a square foot at a 25% margin, using November 9, 2026 material prices. Your crew, plant, and margin change the answer.
How do you follow up on a concrete estimate?
Text on day 3 to check the estimate came through, on day 7 with the pour days you have open, and the week the price runs out to say when you re-price. If the 30-day date passes, send an updated estimate, still with three options. A good, better, and best estimate gives a customer who thinks the top option is too much a cheaper one to say yes to.