Remodeling Estimate Template With a Priced Bathroom Example

Tim Wheeler, Co-founder of ServicePro.coTim WheelerCo-founder, ServiceProLast updated November 9, 2026Checked by Tim Wheeler on November 9, 202615 min readMarketing
Remodeling Estimate Template With a Priced Bathroom Example

For every trade: Contractor Estimate Template With Good, Better, and Best Options

A remodeling estimate template lists the fixed work, the allowances, and three options

A remodeling estimate template lists the work you will do at a fixed price, the allowances for the things the customer still has to pick, and a price for each option. In our example, a 5 by 8 foot hall bathroom with a new tub, tile, vanity, and toilet comes to $10,985 for Good, $11,725 for Better, or $12,150 for Best.

Those prices use materials priced at Lowe's on November 9, 2026, a labor rate built from Bureau of Labor Statistics pay data, and example hours. The template below is ready to copy. The sections after it show where each number comes from, so you can put in your own.

For a market check, Angi's bathroom remodel cost guide, updated October 27, 2026, puts the national average at $12,156 across 28,374 projects, with most homeowners paying $6,651 to $17,662. The Journal of Light Construction's 2025 Cost vs. Value report puts a midrange bath remodel at $26,138, for an update of a 5 by 7 foot bathroom with a porcelain-on-steel tub, a ceramic tile surround, a standard toilet, and a solid-surface vanity top. Our example sits inside Angi's range and well under the Cost vs. Value figure.

What a remodeling estimate needs, in order:

  • Your business name, phone, and license number if your state issues one
  • The customer, the job address, the date, and the date the price ends
  • The scope: what comes out, what goes in, and what stays
  • Fixed-price lines for the work you control
  • Allowances for the items the customer picks
  • Three options, add-ons, and the terms

Copy this remodeling estimate template

Fill in the brackets. Delete any line that does not fit the job. A remodeling quote template is the same document; many remodelers call it a quote when the price is fixed.

[Your Town] Remodeling | [phone] | [email] | License #[number, if your state issues one] Estimate #[number] | Date: [date] | Good through: [date, 30 days out] Customer: [name] | Job address: [address]
Scope Room: [room name], [length] by [width] feet, [height] foot ceiling Remove: [tub, tile, vanity, toilet, flooring, and so on], and haul it away Install: [tub model], [backer board and waterproofing], tile surround to [height] feet, tile floor, vanity, toilet, and faucets Stays: [layout, window, door, lights, anything you are not touching]
Fixed-price work Demolition and disposal | $[price] Plumbing: new tub, valve, and trim, reconnect vanity and toilet | $[price] Backer board and waterproofing on the tub walls | $[price] Set wall and floor tile, grout, and caulk | $[price] Patch, prime, and paint walls and ceiling | $[price] Permit | $[price]
Allowances (what you can spend on items you choose) Wall tile: $[amount] a square foot, [square feet] square feet Floor tile: $[amount] a square foot, [square feet] square feet Vanity with top: $[amount] Toilet: $[amount] Sink faucet: $[amount] If you choose items that cost more, the difference plus [percent]% is added in writing before we order. If they cost less, you get a credit.
Pick one option Good: [allowance level] | $[price] Better: [allowance level] | $[price] Best: [allowance level] | $[price]
Add-ons you can choose Recessed shower niche | $[price] Replace the exhaust fan | $[price] Grab bar with blocking in the wall | $[price]
Included: all labor, materials listed above, and daily cleanup. Not included: moving walls or plumbing, electrical beyond what is listed, and repairs to rot or framing found after demolition, unless agreed in writing. Changes: any change to the work or price is written down and agreed before the work changes. Payment: [deposit amount allowed in your state] to schedule, $[amount] when tile starts, balance when the job is done. Schedule: about [number] working days, spread over [number] weeks so mortar, grout, and paint can dry.

Fixed-price lines and allowances do different jobs

A fixed-price line is work you control. Demolition, waterproofing, and laying tile cost the same whichever tile the customer picks.

An allowance is a budget for something the customer has not chosen yet. Many customers have not picked a vanity on the day you measure, so the estimate says how much the price includes for one.

Name the product when you can. California's contractor board says a home improvement contract should describe the products and work in detail, including dimensions, colors, material quantities, and model numbers. A model number leaves nothing to argue about. An allowance is for the items still open.

Set each allowance from a real shelf price, rounded up so a full box fits:

  • Wall tile. A carton of Artmore 3 by 6 inch polished ceramic subway tile was $69.79 for 10.97 square feet. The example needs 66 square feet, which is 7 cartons, or $488.53. A $7.50 a square foot allowance, $495 in all, covers it. An allowance of $6.50 would not, because tile comes in whole cartons.
  • Toilet. The American Standard Champion was $199 on sale, down from $249. Set the allowance from the regular price, $250, so it still covers the toilet when the sale ends.

Write down what happens when the customer goes over or under. In the template, an overage is added with a set markup, in writing, before you order, and a choice under the allowance is a credit.

Measure the bathroom and count the materials

The example is a 5 by 8 foot hall bathroom with a 60 inch tub along the 5 foot wall. The layout stays the same. Tile goes 6 feet up the three tub walls, and the rest of the walls are painted.

SurfaceMathSquare feet
Back wall above the tub5 x 630
Two end walls above the tub2 x 2.5 x 630
Tub walls total60
Floor, less the tub5 x 8 minus 5 x 2.527.5

Buy about 10% more tile than the surface for cuts and breakage. That is 66 square feet of wall tile and 31 square feet of floor tile.

Count the rest from the maker's coverage:

  • Backer board. A 3 by 5 foot sheet covers 15 square feet. The 60 square feet of tub walls is 4 sheets. Buy 5 for the cuts around the valve.
  • Waterproofing. Mapei's data sheet for Mapelastic AquaDefense lists 60 square feet per 1 gallon pail for two coats, and says to let the second coat dry "30 to 50 minutes before installing tile or stone." One gallon covers the tub walls exactly, so buy 2 for the corners and the tub flange.
  • Thinset. Mapei's sheet for Large-Format Floor and Wall Tile Mortar lists 75 to 90 square feet per 50 pound bag with a 1/4 inch square-notched trowel, which covers the wall tile, and 38 to 45 square feet with a 1/2 inch trowel, which covers the 12 by 24 inch floor tile. That is 2 bags.
  • Grout. One 25 pound bag of sanded grout covers a room this size.

The same sheet says to wait 8 to 16 hours before grouting walls and 24 to 48 hours before grouting floors. Those waits are why a small bathroom takes weeks, not days, and they belong in your schedule line.

Material prices, opened November 9, 2026

These are Lowe's prices for the store in Seekonk, Massachusetts, opened November 9, 2026. Store prices vary, so check your own store or supply house before you send an estimate.

ItemPriceExample usesLine total
American Standard Princeton steel tub, 30 x 60 in.$239.001$239.00
Delta Foundations tub and shower faucet with valve$89.001$89.00
Durock 1/2 in. 3 x 5 ft cement backer board$15.855$79.25
Mapei AquaDefense waterproofing, 1 gal$55.982$111.96
Mapei Large-Format thinset, 50 lb$33.982$67.96
Mapei Keracolor sanded grout, 25 lb$20.481$20.48
Supplies: screws, tape, caulk, patch, primer, paint, wax ring, supply linesExample1$250.00
Total$857.65

The supplies line is an example; use your own from recent jobs.

The items the customer chooses are priced as allowances, from these shelf prices on the same day:

ItemShelf priceGood / Better / Best allowance
Wall tile, per sq ft: Satori 3 x 6, Artmore 3 x 6, Affinity 3 x 6$0.13 a piece (0.12 sq ft), $6.37, $8.09$1.50 / $7.50 / $8.50
Floor tile, per sq ft: Daltile 12 x 24 porcelain$4.55 a piece (1.95 sq ft), $2.34 a sq ft$2.50 for all three
Vanity with top: Project Source Davies, Style Selections Morriston, allen + roth Rian$344, $399, $594$350 / $400 / $600
Toilet: Project Source Pro-flush, American Standard Champion, Kohler Elliston Tall$99, $199 on sale, $299$100 / $250 / $300

The sink faucet allowance in the example, $100, $150, or $200, is an example amount. Price the faucet the customer wants.

Price labor from what an hour really costs you

The labor rate on an estimate is not the wage. It has to cover the wage, the cost of employing someone, the hours nobody pays for, and your overhead and profit. Here is one way to build it, with example numbers after the wage.

  • Wage. The Bureau of Labor Statistics puts median pay for carpenters at $29.12 an hour in 2025. For comparison, flooring installers and tile and stone setters had a median of $26.15 an hour.
  • Cost to employ. In construction, wages were 69.5% of total compensation in June 2026. The rest is payroll taxes, insurance, and benefits. So $29.12 ÷ 0.695 = $41.90 an hour.
  • Hours nobody pays for. Driving, picking up tile, and writing estimates are paid hours you can't bill. If 6 of every 8 paid hours are billable, each billable hour carries $41.90 x 8 ÷ 6 = $55.87.
  • Overhead and profit. The truck, the dumpster account, insurance, the phone, and the profit that lets you grow. Adding 50% gives $55.87 x 1.5 = $83.80. Round to $85 an hour.

Every number in that list after the wage is an example. Put in your own billable hours and overhead.

Price subcontractors from their written quote, plus a markup. Many remodelers sub out the plumbing. Angi lists plumbers at $45 to $200 an hour. The BLS median wage for plumbers, pipefitters, and steamfitters was $30.67 an hour in 2025, so the rest of a plumber's rate is their own overhead and profit. The example uses a $1,000 plumbing quote, 8 hours at $125, plus 15% for scheduling the plumber and standing behind the work. Use your plumber's real number.

Sam is the AI office manager that never sleeps.

He books jobs, sends invoices, and answers your customers, all by text. He checks with you before anything goes out.

Free plan, no credit card. Sam answers new customers on Pro. Or text (833) 365-7267.

SamYour office manager

Hi, I'm Sam. Text me what you need done and I'll take care of it.

How do I get started?

Worked example: a 5 by 8 foot hall bathroom priced at $10,985

This is the Good option. The hours are example hours for a two-person crew in a house built after 1978, with no rot behind the old tile. Time your own crew and use those.

StepExample hours
Remove tile, tub, vanity, and toilet, and load the trailer12
Set the tub, add blocking, fix small framing problems6
Hang backer board, tape seams, two coats of waterproofing8
Set 66 square feet of wall tile16
Set 31 square feet of floor tile8
Grout, caulk, and seal6
Patch and finish drywall, three coats10
Prime and paint walls and ceiling8
Set vanity, toilet, faucet, trim, and accessories8
Clean up, punch list, and walkthrough with the customer4
Total86

The price:

LineMathAmount
Materials$857.65$857.65
Allowances, Good$99 + $77.50 + $350 + $100 + $100$726.50
Materials and allowances with markup$1,584.15 + 15%$1,821.77
Labor86 hours x $85$7,310.00
Plumber$1,000 + 15%$1,150.00
DisposalExample$450.00
PermitExample$250.00
Total$10,981.77

Quote it as $10,985. The disposal and permit lines are examples inside Angi's ranges: $100 to $800 to haul off old tile and fixtures, and $100 to $1,000 for permits. Call your building department for the real permit fee before you send the estimate.

Check it against the market. Angi's national average is $12,156, and most bathrooms land between $6,651 and $17,662, so $10,985 is in the middle. If you come in far under, check your hours first: demolition and drywall are where small jobs run long.

These are example numbers. The arithmetic is exact.

Good, better, and best options are three levels of allowances

For a remodel, keep the work the same and change the allowances. The tub, the waterproofing, and the hours stay put; the tile, vanity, toilet, and faucet change. The customer sees exactly what the extra money buys.

OptionWhat changesAllowancesPrice
GoodBasic white tile, cultured marble top, basic toilet$726.50$10,985
BetterPolished subway tile, engineered stone top, soft-close toilet$1,372.50$11,725
BestPremium subway tile, walnut vanity, tall-height toilet$1,738.50$12,150

How the other two were priced, as examples:

  • Better is $1,372.50 in allowances ($495 wall tile, $77.50 floor tile, $400 vanity, $250 toilet, and $150 faucet). Plus the fixed materials and 15% markup, that is $2,564.67. With the same labor, plumbing, disposal, and permit, the total is $11,724.67, quoted at $11,725.
  • Best is $1,738.50 in allowances ($561 wall tile, $77.50 floor tile, $600 vanity, $300 toilet, and $200 faucet). With markup, materials are $2,985.57, and the total is $12,145.57, quoted at $12,150.

Only $1,165 separates Good from Best, because labor, $7,310, is about two thirds of the Good price.

Add-ons are extras the customer can say no to. Keep the list short and price each one on its own:

Add-onHow it is pricedExample price
Recessed shower nicheAbout 5 hours at $85, plus framing and a niche form$500
Replace the exhaust fanYour electrician's quote, plus markup$450
Grab bar with blocking in the wallAbout 1.5 hours, plus the bar$150

All three add-on prices are examples. Leave out anything the job needs to work. If the subfloor is soft, that is a written change, not an add-on. Our contractor estimate template uses the same options and add-ons layout for smaller jobs.

Make the price good for 30 days, and put the terms on the estimate

Write the date your price ends on the estimate. The example uses 30 days, because material prices have been climbing.

The Producer Price Index for construction materials, published by the Bureau of Labor Statistics and charted by the St. Louis Fed, went from 341.005 in September 2025 to 378.610 in September 2026. That is an 11.0% rise in a year. A 30 day window keeps your allowances and material lines close to what you will pay at the counter. If your prices have gone up since, our guide to raising your prices shows how to tell your customers.

Terms worth writing on every remodeling estimate:

  • Deposit. Some states cap it. In California, a home improvement down payment cannot be more than $1,000 or 10% of the contract price, whichever is less, with no exception for special-order materials. Check your own state before you write a deposit amount.
  • Changes. California also requires a written change order, signed by the customer and the contractor, before the change. Rot behind old tile is the change you will meet most often.
  • Three-day right to cancel. If you sign the job at the customer's home, the FTC's Cooling-Off Rule gives them until midnight of the third business day to cancel, and you must give them a copy of the contract and two copies of a cancellation form. Sales at a home under $25 are not covered, so a remodel almost always is.
  • Old paint. In homes built before 1978, the EPA's lead rule covers "anyone who is paid to perform work that disturbs paint," including sole proprietors. Demolition of painted surfaces is covered regardless of square footage. If you are gutting a bathroom in an older house, say so on the estimate and follow the rule.

When the customer says yes, our contractor contract template covers the rest of the terms. This is not legal advice, and rules differ by state.

Follow up 3 days after you send it, then before the price ends

A quiet estimate is not always a no. The customer may be comparing bids or shopping for a vanity. Three short follow-ups cover it.

  • Day 3: a short text that makes it easy to answer.
  • Day 10: a call. Questions about allowances are easier to answer by voice.
  • 3 days before the good-through date: a last text with the date.

Copy and change these:

Hi [Name], it's [Your name] at [Business]. Just checking you got the estimate for the bathroom. Happy to walk you through the three options.
Hi [Name], it's [Your name]. If you're still choosing tile or a vanity, the allowances on the estimate are what you can spend on each one. Send me a photo or a link of anything you like, and I'll tell you if it fits.
Hi [Name], the price on your bathroom estimate is good through [date]. After that I'll need to recheck material prices. Want me to hold a start date for you?

After the third message, stop. If they come back later, recheck the material prices and allowances before you start.

Where ServicePro fits

ServicePro is home services software, and every business, Free plan included, can send estimates with options and add-ons. You build Good, Better, and Best and the add-on lines, and the customer opens the estimate on their phone, picks an option, ticks the add-ons they want, and approves it, with no login. The approved lines become the work on the job, so you can invoice it and take card payments through a pay link. Estimates with no answer after three days show up for you with Text and Call buttons.

ServicePro estimates have no e-signature, no photos, no expiry date field, and no PDF to print, and nothing follows up with the customer for you. Write the good-through date and allowance terms in the estimate, and send the follow-ups yourself. The Free plan also builds a website from your Google Business Profile, with five service pages and a booking page where customers request a time. Get the free website.

How this post was made: drafted with AI from the sources linked on this page. Figures and links were checked on November 9, 2026.

Frequently Asked Questions

What should a remodeling estimate include?

A remodeling estimate should list the scope, the fixed-price work, an allowance for each item the customer still has to pick, a price for each option, add-ons, what is and is not included, payment terms, how changes are handled, and the date the price ends. In our example, a 5 by 8 foot bathroom with a new tub and tile is priced at $10,985, $11,725, or $12,150 for three allowance levels.

What is an allowance on a remodeling estimate?

An allowance is the amount the price includes for an item the customer has not chosen yet, such as tile, a vanity, or a toilet. Set it from a real shelf price, rounded up so whole cartons fit. In our example, 66 square feet of polished subway tile cost $488.53 in 7 cartons, so the allowance is $7.50 a square foot, or $495. Overages are added in writing, and savings come back as a credit.

How much does a bathroom remodel cost?

Angi's guide, updated October 27, 2026, puts the national average bathroom remodel at $12,156 across 28,374 projects, with most homeowners paying $6,651 to $17,662. The Journal of Light Construction's 2025 Cost vs. Value report puts a midrange 5 by 7 foot bath remodel at $26,138. Our 5 by 8 foot example, with Lowe's prices from November 9, 2026, came to $10,985 to $12,150 depending on the option.

How long should a remodeling estimate be good for?

Thirty days is a sensible limit for a remodeling estimate. The Producer Price Index for construction materials rose 11.0% from September 2025 to September 2026, so a price older than a month may not cover your materials or your allowances. Write the good-through date on the estimate and say that you will recheck prices after it. ServicePro estimates have no expiry field, so put the date in the estimate text.

How do I price labor on a remodeling estimate?

Start from the wage, then add the cost of employing someone, the hours you can't bill, and overhead and profit. The BLS median for carpenters was $29.12 an hour in 2025. Dividing by 0.695, the wage share of construction compensation, gives $41.90. At 6 billable hours in 8 that is $55.87, and 50% for overhead and profit makes about $85 an hour. Only the wage and wage share are published figures.

Is a remodeling quote the same as an estimate?

In practice, yes. Many remodelers say quote when the price is fixed and estimate when it may change, but the document is the same: the scope, fixed-price lines, allowances, options, terms, and a good-through date. Whatever you call it, say in writing which lines are fixed and which are allowances. In our example, labor of 86 hours at $85 is fixed, and the tile, vanity, toilet, and faucet are allowances.

How much deposit can a remodeler take?

It depends on your state. In California, the Contractors State License Board says a home improvement down payment cannot be more than $1,000 or 10% of the contract price, whichever is less, with no exception for special-order materials. On our $10,985 example, that cap would be $1,000. Other states set their own rules, so check with your state's contractor licensing agency before you write a deposit amount. This is not legal advice.

Built for remodeling contractorsSee where a Jobsite ranks for remodeling searches, and what it costs.
Tim Wheeler, co-founder of ServiceProDaniel Holliday, co-founder of ServicePro

“Service pros don’t need another piece of software. They need a system that helps them win online: get found on Google, book the job, and get paid. That’s what we built, and Sam runs it for you by text.”

Tim Wheeler & Daniel Holliday · Co-founders, ServicePro

Meet Sam →

Get your free website for remodeling contractors.

A website for your remodeling business, ready in a few minutes. We keep it current, and we never charge per lead.

Free plan · No credit card

Or talk to a co-founder first. Book a call