Remodeling Contract Template: 15 Clauses to Copy
For every trade: Contractor Contract Template: 17 Clauses to Copy
A remodeling contract template needs 15 clauses and a payment schedule by milestone
A remodeling contract template needs 15 clauses: scope and drawings, dates, price, allowances, a payment schedule by milestone, change orders, hidden conditions, permits, site rules, subcontractors and lien waivers, insurance, warranty, the right to cancel, disputes, and signatures. State law sets some of them for you. In California, a written contract is required for all home improvement projects over $500, and the down payment cannot be more than $1,000 or 10 percent of the contract price, whichever is less.
A remodel needs more paper than a service call. The job changes as you open walls, money moves before the work is done, and other people can put a lien on the house. In California, unpaid subcontractors, suppliers, and laborers may record a mechanics lien even when the contractor was paid in full. Lien waivers close that gap.
The template below is written for a kitchen or bathroom remodel in an owner-occupied home.
This is not legal advice. It is a starting point built from the public rules linked on this page. Some states require exact wording, type sizes, and notices, so have a local construction lawyer read your final version once.
Copy this remodeling contract template
Fill in the brackets and delete the notes that start with "Example," "Choose," or "Optional." Where your state sets its own wording, such as a lien or cancel notice, use the state's.
Home Improvement Agreement This agreement is between [Business name], [business address], [phone], [email], license or registration number [number] ("we"), and [Owner name or names], [mailing address], [phone], [email] ("you"), for work at [property address]. It is signed on [date].
1. Scope of work. We will do the work described in Exhibit A, using the materials listed there by brand, model, color, and size where known. The work follows the drawings in Exhibit B, revision [number], dated [date]. If Exhibit A and Exhibit B disagree, Exhibit A controls. The price includes cleanup and hauling away our debris. Not included: [Example: painting outside the bathroom, moving furniture, repairs to anything behind walls that we have not seen yet. See clause 7.]
2. Dates. We expect to start on or about [date] and to finish the work, except for punch list items, on or about [date]. The finish date moves by the days lost to change orders, failed inspections we did not cause, late selections or deliveries, and weather we cannot work in.
3. Price. The total price is $[amount], including the allowances in clause 4 and the permit fees in clause 8. [Choose: Sales tax is included. / Sales tax is added as shown in Exhibit A.]
4. Allowances. The price includes these allowances for items you will choose: [Example: floor and wall tile, $[amount] per square foot, installed area [number] square feet; light fixtures, $[amount] total; vanity faucet, $[amount].] If your choice costs more than the allowance, the difference is added by change order. If it costs less, the difference is credited on the final invoice. We need your selections by [date] to keep the schedule.
5. Payment schedule. You will pay as shown in Schedule B. Each payment is due within [3] days after the milestone in Schedule B is done. No payment will be more than the value of the work done and materials delivered at that point. The final payment is due when the final inspection has passed and the punch list is done.
6. Change orders. Any change to the work, the price, or the dates needs a written change order signed by both of us before the changed work starts. Each change order states the work, the price change, the new total, and any change to the finish date.
7. Hidden conditions. If we find something we could not see before we started, such as rot, mold, damaged framing, or wiring that is not to code, we will stop work in that area, show you, and give you a change order. We will not fix it without your signed approval, except to make it safe.
8. Permits and inspections. We will get the building permits the work needs and schedule the inspections. Permit fees are [Choose: included in the price / billed at cost]. Work that needs an inspection stays open until it passes.
9. The site. We will work [Monday through Friday, 8:00 a.m. to 5:00 p.m.]. You will clear the work area of personal belongings before we start and keep children and pets out of it. We will protect floors and seal off the work area from dust, and leave the site broom clean each day. [Optional, for homes built before 1978: We will give you the EPA Renovate Right pamphlet before work starts and follow lead-safe work practices. Our EPA lead-safe firm certification number is [number].]
10. Subcontractors, suppliers, and lien waivers. We will give you a list of the subcontractors and suppliers on this job before they start. With each payment after the first, we will give you lien waivers from ourselves and from any subcontractor or supplier paid from the last payment. [Add your state's required mechanic's lien notice here, in the type size the law sets.]
11. Insurance. We carry general liability insurance of $[amount] per occurrence and workers' compensation as our state requires. We will give you a certificate before we start. [Optional, for New York: Your property insurance company is [name], [address], [phone].]
12. Warranty. We warrant our workmanship for [1 year] from the date the work is done. If something we built fails because of how we did the work, we will fix it at no charge. Manufacturer warranties on fixtures, appliances, and materials pass to you, and we will give you copies. This warranty does not cover damage from misuse, normal wear, or work done by others.
13. Your right to cancel. [Use your state's wording. Example: You may cancel this agreement at any time before midnight of the third business day after you sign it. See the attached Notice of Cancellation.]
14. Problems and ending the agreement. If either of us thinks the other has broken this agreement, that person will say so in writing and give [10] days to fix it. If it is not fixed, we will try to settle it in person, then by [mediation in (county)]. If you end the agreement, you pay for the work done and materials ordered up to that day.
15. Signatures. This agreement, Exhibit A, Exhibit B, Schedule B, and any signed change orders are the whole agreement. Do not sign this contract if there are any blank spaces. [Massachusetts: this line must be in 10-point bold type or larger, directly above the signatures.] [Business name], by [name and title], [signature], [date] [Owner name], [signature], [date]
Attach these three forms:
Schedule B: Payment schedule [List each milestone, the payment due when it is done, and the running total. See the worked example below.]
Change Order No. [number] Job: [property address]. Date: [date]. Change: [what is added, removed, or different]. Price change: [+ or -] $[amount]. Previous total: $[amount]. New total: $[amount]. Finish date change: [number] days. New finish date: [date]. Owner [signature], [date]. Contractor [signature], [date].
NOTICE OF CANCELLATION [Date of transaction] You may CANCEL this transaction, without any Penalty or Obligation, within THREE BUSINESS DAYS from the above date. [Use the full FTC form or your state's form, in two copies.]
Scope and drawings: describe the job so a stranger could price it
A vague scope starts arguments. "Remodel hall bathroom" can mean new paint and a faucet or a gut to the studs. California's contractor board says the contract should describe the products and how the work will be done "in detail," including cleanup and removal of debris. Massachusetts requires "a detailed description of the work to be done and the materials to be used" on residential contracts over $1,000.
What goes in Exhibit A:
- Each area and what happens there. "Remove tub and surround to studs. Install 60 inch curbless shower with linear drain." Not "new shower."
- Materials by name. Brand, model, color, and size for anything already picked. Allowances for the rest.
- What you are not doing. Painting the hallway, patching the ceiling below, moving the washer. Write it down so nobody assumes.
- Who buys what. If the homeowner supplies the vanity, say so, and say who answers for it if it arrives broken.
Drawings. Put a revision number and date on every drawing and name that revision in clause 1. When the layout changes, issue a new revision with a change order, so there is only ever one version of the plan on site.
If you price from a written estimate first, our contractor estimate template shows how to lay out line items so they carry straight into Exhibit A.
Change orders: get a signed price before the changed work starts
A change order is a short written agreement that changes the scope, the price, or the dates. Some states require one. In California, a change to the contract price "MUST be done with a written change order that becomes a part of the contract", signed by the customer and contractor prior to the change. In New Jersey, home improvement contracts over $500 and all changes in their terms must be in writing, signed by all parties.
Three habits that get you paid for changes:
- No change order, no work. If the homeowner asks for an extra outlet on Tuesday, write it up and get a signature before the electrician runs wire. Extra work with no signed change order is hard to collect for.
- Show the new total every time. Each change order lists the previous total and the new one, so the final invoice holds no surprises.
- Move the date when the work grows. Write the added days on the form. Clause 2 moves the finish date by those days.
Hidden conditions are the change orders nobody plans for. Clause 7 sets the steps before it happens: stop, show the homeowner, write it up, and wait for the signature.
Allowances: a worked example shows how the price moves
An allowance is a set amount in the price for something the homeowner will choose later, such as tile or light fixtures. It lets you sign before every selection is made and puts the cost of upgrades on the homeowner, in writing. Write each one as a dollar amount and say how it is measured: per square foot, per fixture, or as a lump sum.
An example with made-up figures. Sarah M. is remodeling a bathroom. The contract carries a tile allowance of $8 per square foot for 120 square feet, which is $960 for tile.
| Sarah's choice | Price per square foot | Tile cost for 120 sq ft | Change to the price |
|---|---|---|---|
| Stays in the allowance | $8 | $960 | None |
| Picks a $14 tile | $14 | $1,680 | +$720 by change order |
| Picks a $6 tile | $6 | $720 | -$240 credit on the final invoice |
Three things to decide before you sign:
- Materials only, or labor too? A mosaic tile takes longer to set than the tile you priced. Say in clause 4 whether labor changes.
- Do you mark up the overage? If you add your markup to the difference, write the percentage in clause 4.
- When are selections due? Put the date in clause 4, and let clause 2 move the finish date if a selection is late.
Payment schedule by milestone: tie each payment to finished work
A milestone schedule pays you as the job moves and shows the homeowner what each payment buys. Deposit and progress payment rules differ by state:
| State | Down payment rule | Progress payments |
|---|---|---|
| California | Lesser of $1,000 or 10 percent of the contract price, with "no exceptions for special order materials" | Must show the amount of each payment and the work it pays for, and cannot exceed the value of the performed work |
| Massachusetts | Up to the greater of one-third of the total price or the actual cost of special-order or custom materials | Payment schedule with each amount in dollars, and no final payment demanded until the work is done |
| New York | No cap in the contract statute, but you must deposit payments received before completion or post a bond and tell the owner so in the contract | A schedule showing each payment "as a sum in dollars and cents" and the stage of work due before it, with each payment bearing a reasonable relationship to the work |
An example with made-up figures. Dave's crew signs a $36,000 bathroom remodel. The down payment limit changes a lot by state:
- California: 10 percent is $3,600, so the lesser amount, $1,000, is the most he can take at signing.
- Massachusetts: one-third is $12,000. If special-order materials cost more than that, their actual cost is the limit.
A schedule that fits the California rule:
| Milestone | Payment | Running total |
|---|---|---|
| Down payment at signing | $1,000 | $1,000 |
| Demolition done, rough plumbing and electrical pass inspection | $10,000 | $11,000 |
| Walls closed, shower waterproofing done | $8,000 | $19,000 |
| Tile, vanity, and fixtures set | $11,000 | $30,000 |
| Final inspection passed, punch list done | $6,000 | $36,000 |
Make milestones things anyone can see. "Rough-in passes inspection" is a fact. "50 percent done" is an argument. Keep the final payment large enough that you both care about the punch list, and send each invoice the day the milestone is done. Our contractor invoice template shows what to put on each one.
Sam is the AI office manager that never sleeps.
He books jobs, sends invoices, and answers your customers, all by text. He checks with you before anything goes out.
Free plan, no credit card. Sam answers new customers on Pro. Or text (833) 365-7267.
Hi, I'm Sam. Text me what you need done and I'll take care of it.
How do I get started?
Permits, inspections, and lead paint: say who handles each
Permits. Say in the contract who gets them. California's contractor board says the contract needs written direction as to who will get the necessary permits, and its consumer guide tells homeowners to ask whether permit fees are included in the contract price. Massachusetts goes further for homeowner contracts: the contract must list the permits the work needs, say the contractor must get them, and say that homeowners who get their own permits are excluded from the state's guaranty fund.
The template has you pull the permits, which keeps inspections on your schedule.
Lead paint in older homes. If the house was built before 1978, the EPA's Renovation, Repair and Painting rule likely applies. Under it, you must distribute EPA's lead pamphlet to the owner and occupants before renovation starts, get confirmation that they received it, and retain records for three years. All firms must be certified (even sole-proprietors).
The rule does not apply to minor work that disturbs six square feet or less of paint per room inside, or 20 square feet or less on the exterior, but window replacement and demolition never count as minor, so a kitchen or bathroom gut in a pre-1978 house is covered. The optional line in clause 9 puts the pamphlet, lead-safe practices, and your certification number in writing.
Lien waivers and the mechanic's lien notice: protect the homeowner and yourself
A mechanic's lien is a claim against the property by someone who worked on it and wasn't paid. California's contractor board warns that even if the contractor is paid in full, unpaid subcontractors, suppliers, and laborers may record a mechanics lien, and the owner could be forced to pay twice. Clause 10 offers lien waivers up front for that reason.
Two states, two notice rules:
- California requires contractors to give a "Mechanics Lien Warning". Suppliers and subcontractors must give the owner a "Preliminary Notice" within 20 days of delivering materials or beginning work.
- New York requires the contract to warn that the owner "may have a valid legal claim against your property known as a mechanic's lien" in clear, bold type.
The four kinds of waiver. California's lien waivers must follow, substantially, one of the forms in Civil Code sections 8132, 8134, 8136, and 8138. The four forms work like this:
| Waiver | When to use it | What it says |
|---|---|---|
| Conditional, progress | Before a progress payment clears | Good only if the payment is actually paid |
| Unconditional, progress | After a progress payment clears | You received that payment |
| Conditional, final | Before the final payment clears | Good only with evidence of payment |
| Unconditional, final | After the final payment clears | You received the final payment |
Hand over a conditional waiver with each invoice and an unconditional one once the money is in your account. Never sign an unconditional waiver for money you haven't received.
Warranty: put what you promise in writing, with a time limit
California's contractor board tells homeowners to get any warranty for labor and materials in writing. New Jersey requires the contract to include "a statement of any guarantee or warranty" the seller makes. Clause 12 does three things:
- Sets a length. Pick a length for workmanship you can stand behind, counted from the day the work is done, and write it down.
- Passes along manufacturer warranties. Hand over the paperwork for the faucet, fan, and flooring.
- Says what isn't covered. Misuse, normal wear, and work by others.
The federal warranty law has a catch for remodelers. The FTC says the Magnuson-Moss Warranty Act does not apply to warranties on services. Only warranties on goods are covered. But if you warrant both the parts provided for a repair and the workmanship in making that repair, the Act does apply, and its disclosure rules cover written warranties on consumer products costing more than $15. If your warranty covers materials you supply, have your lawyer check it against the FTC guide.
The 3-day right to cancel: the FTC rule and three state rules
If you sign the contract at the homeowner's house, cancel rules apply. The FTC's Cooling-Off Rule covers sales of $25 or more made at the buyer's residence. The buyer can cancel until midnight of the third business day after the sale, and you must give them two copies of a cancellation form and refund their money within 10 days if they cancel. The rule excludes repair or maintenance work the buyer asked for, but a remodel is rarely repair or maintenance, so plan on it applying.
The form is captioned "NOTICE OF CANCELLATION" or "NOTICE OF RIGHT TO CANCEL" and printed in "ten point bold face type," and you must not misrepresent in any manner the buyer's right to cancel.
States add their own rules on top:
| State | Cancel period | What else to know |
|---|---|---|
| California | Three business days, or five if the buyer is 65 or older | Refund within 10 days of the cancel. Doesn't apply if the contract is negotiated at your place of business |
| New York | Until midnight of the third business day after signing | The contract itself must say so. Applies to contracts over $500 |
| Massachusetts | Three days, by the notice the contract must include | Applies to contracts over $1,000. The owner gets a signed copy before any work begins |
The emergency exception is narrow. New York and the FTC allow a waiver only for a true emergency the owner asked you to fix, with a separate, dated statement in the buyer's handwriting. A kitchen remodel is not an emergency. Don't start work or order special materials until the cancel period ends. For the general version of these rules across trades, see our contractor contract template.
Where ServicePro fits
ServicePro is home services software. Send the remodel as an estimate with options and add-ons, such as a standard shower or a curbless upgrade, that the homeowner opens on their phone and approves with no login. The approved estimate becomes the work on the job. Then send an invoice at each milestone in Schedule B, and the homeowner pays by card through a pay link. ServicePro has no e-signature and no contract forms, so an approval is a yes on price, not the signed contract or change order your state may require. Keep the signed paperwork yourself.
The Free plan is $0 with no card and builds a website from your Google Business Profile, with five service pages and a booking page where customers request a time. Your own domain works on every plan. Pro is $99 a month with no contract and adds a toll-free number that forwards calls to your cell and two-way texting with customers after carrier verification. Get the free website
How this post was made: drafted with AI from the sources linked on this page. Figures and links were checked on November 9, 2026.
Frequently Asked Questions
What should a remodeling contract include?
A remodeling contract should include 15 clauses: scope and drawings, start and finish dates, price, allowances, a payment schedule by milestone, change orders, hidden conditions, permits, site rules, subcontractors and lien waivers, insurance, warranty, the right to cancel, disputes, and signatures. California requires a written contract for home improvement jobs over $500, and Massachusetts for jobs over $1,000. Attach a change order form and a notice of cancellation.
How much of a down payment can a remodeling contractor ask for?
It depends on the state. In California, the down payment cannot be more than $1,000 or 10 percent of the contract price, whichever is less, with no exception for special-order materials. Massachusetts allows up to one-third of the price or the actual cost of special-order materials, whichever is greater. New York sets no cap in its contract statute but requires payments received before completion to be deposited or bonded.
Does a remodeling contract need a 3-day right to cancel?
Usually, yes. The FTC Cooling-Off Rule covers sales of $25 or more made at the buyer's home and gives three business days to cancel. California gives three business days, or five if the buyer is 65 or older. New York requires the contract itself to tell the owner they may cancel until midnight of the third business day after signing. Attach a notice of cancellation in two copies.
What is a change order in a remodeling contract?
A change order is a short written agreement that changes the work, the price, or the finish date after the contract is signed. California requires a change to the contract price to be made by a written change order signed by both sides before the change. New Jersey requires changes to home improvement contracts over $500 in writing and signed. List the old total and the new total on every change order.
What is an allowance in a remodeling contract?
An allowance is a set amount in the price for an item the homeowner picks later, such as tile or light fixtures. If the choice costs more, the difference is added by change order. If it costs less, the homeowner gets a credit. For example, a tile allowance of $8 per square foot for 120 square feet is $960; a $14 tile adds $720. Write selection due dates in the contract.
Do remodeling contractors need to give lien waivers?
Not every state requires them, but homeowners often ask, because unpaid subcontractors and suppliers can file a mechanic's lien even when the contractor was paid. California uses four statutory forms: conditional and unconditional, for progress and final payments. Give a conditional waiver with each invoice and an unconditional one once the money clears. Never sign an unconditional waiver for money you haven't received.
Can I get a remodeling contract signed in ServicePro?
No. ServicePro has no e-signature and no contract forms. You can send the remodel as an estimate with options and add-ons that the homeowner approves on their phone with no login, then send an invoice at each milestone that they pay by card through a pay link. An approval is a yes on price, not the signed contract or change order a state like California requires.